Building Model Images
Ground Breaking Day
Final Site
Expenses So Far.
Description | Contractual Agreements | Amount Paid | Remaining Balance |
Land Purchase | 600,000.00 | 600,000.00 | 0 |
Qarz e Hasna (Loan) to Purchase Land | 225,000.00 | 220,000.00 | 5,000.00 |
Pre Construction Expenses: | |||
Architect: Loveless Porter | 40,329.94 | 40,329.94 | 0 |
Civil Engineers/Land Survey - Ross France | 67,819.00 | 67,819.00 | 0 |
Wetland & GeoTech (ECS Mid-Atlantic) | 11,093.75 | 11,093.75 | 0 |
Prince William County Permit Fees | 12,360.14 | 12,360.14 | 0 |
Compton & Dulling, LLC - (For Zoning & Easement) | 56,873.89 | 56,873.89 | 0 |
Kittelson & Associates, Inc. - (TIA & VDOT) | 40,018.50 | 40,018.50 | 0 |
Ridgewood III Easement | 162,000.00 | 162,000.00 | 0 |
Christopher Consultants (Designed Entrance & Plan Stripping Plan) | 17,880.00 | 17,880.00 | 0 |
Total | 408,375.22 | 408,375.22 | 0 |
TOTAL LAND & EXPENSES | 1,008,375.22 | 1,008,375.22 | |
Misc. Expenses: | |||
Prince William County Property Tax 2016 to-date | 77,189.25 | 77,189.25 | 0 |
CONSTRUCTION ESTIMATE: 4 Million US Dollars | |||
Donation Grid | |||
10,000 | 25,000 | 50,000 | 100,000 |
Fill out the form to pledge donation below
Board Of Directors
Jafar H. Shah
President - 571-288-2488
Syed Arshad Jaffery
Vice President - 202-344-5107
Syed Ali A. Bukhari
General Secretary & Treasurer - 571-216-4683
Zakir H. Zaidi
Programs Director - 540-207-4659
Syed Ajwad Naqvi
Director - 703-606-5998
Syed Asad A. Zaidi
Director - 571-422-0423
Nasir Khan
Director - 540-841-5957
Board Of Trustees
Syed Jawwad Shirazi
Chairman - 703-303-0438
Wazir Chagla
Vice Chairman - 703-321-6582
Jawaid Naqvi
Trustee - 703-909-8647
Syed Shahid Tirmizi
Trustee - 571-437-0120
Syed Zulfiqar Zaidi
Trustee - 703-3428427